The Progress of the Plant
June 2019
NMPP re-entered market outside NamPower
May 2020
NMPP signed PPA Term Sheets with various companies
Jan 2021
NMPP Investors regrouped regarding Debt & Equity
Oct 2022
Engineering redesign & technology selection completed
July 2023
Secured several new offtakers in South Africa and Zambia
Feb 2024
Concluded PPA term sheets, LOIs and Moa's for more than 700MW
2019
2020
Sep 2019
NMPP acquired all rights to the IP of WBPP
Dec 2020
Update IPP license with ECB
2021
2022
2023
2024
March 2021
Application submitted for new IPP & Export licences
Dec 2022
offtaker strategy reviewed and export network studies started
Nov 2023
Discussions progressed with funders for JDA
Oct 2024
Project on target to achieve first power by Q1 2026
May 2018: The ECB renews WBPP IPP Licence, and allows WBPP to seek other off-takers, thus opening up the project to many possibilities.
​
June 2019: NMPP re-entered the energy market
​
September 2019: NMPP acquired all the rights from WBPP
​
January 2020: NMPP engages with potential SAPP Offakers.
​
May 2020: NMPP signed PPA Term Sheet with South African Utility
​
December 2020: IPP license updated
January 2021: NMMP started to the process for new Investors
​
March 2021: New application submitted for new IPP & Export licences
​
January 2022: ECB approved new Generation and Export Licences